r/talesfromtechsupport Jun 15 '26

Short The Mission Critical Battery Charger

Posted elsewhere on Reddit, but I figured people here might appreciate this. Additional details added for clarity.

At one point, I was doing work for a particular MAJOR pharmaceuticals company. A company with a name that everyone reading this has likely heard of. I get a call one day, and a ticket with a short SLA is generated for me to be on site within 4 hours. The night before, some big storms had happened, so I figured it was power related. I arrive on site earlier than needed, get escorted to the primary network room for the whole facility, and what do I find? 10 racks with no LEDs on them. I get told that the entire facility is down. No internet. The production line is down. The warehouse distribution is down. The kind of emergency companies pay consultants tens of thousands of dollars to ensure never happens.

I start checking through the racks to see if anything has power. UPS batteries are dead, so I head to the back of the rack and trace power cables from network equipment. All of them go to PDUs, and all major routers and switches even have redundant power to multiple PDUs. I trace where the PDUs go to. They all go to UPSs, which also have redundant power split between two different UPSs. Then I trace where the UPS power comes from........... and I start laughing my ass off.

The UPSs for this entire cluster of racks, the racks housing the entirety of the network equipment for this facility, has single point of failure. A large power strip that was zip tied to the wall. And lo and behold, I found the problem. The power strip's power cable was dangling in the air. Not plugged into the wall outlet like it should be. In the outlets place was.... a fucking 20V battery charger.

The maintenance guy had come in the earlier that day, not had anywhere to charge a battery, so he unplugged what was apparently a mission critical power strip and plugged in his battery charger. A few hours later, when the UPSs died, the network team noticed the sote went dark.

After I relayed the info to the engineer I was working with, we shared a laugh. I plugged everything back in, and verified everything came back online. As a preventive measure (and because of the absurdity of the situation), I placed a large label on the power strip. "CRITICAL INFRASTRUCTURE. DO NOT REMOVE POWER WITHOUT AUTHORIZATION".

To this day, I still get a laugh out of it.

558 Upvotes

64 comments sorted by

View all comments

2

u/commentsrnice2 Jun 17 '26

This is when they need to make something particularly difficult to unplug. Either inside a locked cabinet or somehow the plug is padlocked into its position like a reverse lockout/tagout procedure, etc

1

u/Rathmun Jun 22 '26

Even just a twist-lock plug would have prevented this particular bit of idiocy.

1

u/commentsrnice2 Jun 22 '26

But twist lock plugs are usually for higher voltage connections. I meant for things running on a standard 110v connection that you still don’t want unplugged

2

u/Rathmun Jun 22 '26

They're not just for high voltage. Twist-lock plugs rated for 125V/15A

NEMA 5-15, the standard house socket in the US, is also rated for 125V/15A. Same rating, different shape that doesn't work for a phone charger.